Task Order Guidelines
THE
MOST STREAMLINED IA CONTRACT PROCESS POSSIBLE!
DISA's
Deputy Director for C4 & Intelligence Program Integration (DISA/D2) performs
the functions of program manager and steward for the 'I Assure' contracts.
DISA works in partnership with customers in DISA, DoD components and other
Federal Agencies to understand how the 'I Assure' Contract can be used to
meet the customer's information assurance requirements. Through regular in-process
reviews, DISA ensures the work being performed is in accordance with, and
can be integrated with, approved DoD standard communications, security, data
and other defined technical solutions.
STEP
1 - DOCUMENT PREPARATION
The Task Monitor (TM) prepares the requirements package that is the basis
for processing and awarding the 'I Assure' task order. It includes the statement
of work, purchase request and other documents listed in the guidelines checklist.
The forms and checklists are available from the web site http://www.ditco.disa.mil/hq/contracts/iachar.asp
with a click on Task_Order_Guidelines in the yellow bar. The customer forwards
the package to the DISA Contract Officer's Representative electronically at
Thompsol@ncr.disa.mil.
STEP
2 - DISA CONTRACT OFFICER'S REPRESENTATIVE (COR) REVIEWS AND FORWARDS REQUIREMENTS
PACKAGE
The COR ensures the requirements package is complete, compliant, and within
the scope of the 'I Assure' Contract. Then the COR forwards the package to
the Contracting Officer at the Defense Information Technology Contracting
Organization (DITCO) at Scott Air Force Base, IL.
STEP
3 - CONTRACTING OFFICER (KO) REQUESTS PROPOSAL FROM CONTRACTORS
Electronically, the KO requests proposals from all 'I Assure' prime contractors
unless an exception has been granted. Each contractor is generally allowed
7-14 days to prepare and submit proposals. However, more or less time may
be necessary based on the requirements. Each task order proposal request issued
lists the due date, technical proposal page limitations, evaluation criteria
and order of importance.
STEP
4 - SRA PREPARES TECHNICAL & COST PROPOSAL AND TRANSMITS ELECTRONICALLY
The technical proposal may be written and/or oral as stipulated. The cost
proposal must be submitted in writing. The technical proposal will be no more
than 10 pages, stating compliance with or exception to SOW requirements, risks,
assumptions, and conflict of interest issues. It must include as a minimum
the technical approach, key personnel, hours of personnel by labor categories,
and other direct costs. It will also include period of performance, government
furnished equipment and information, security (including clearance level),
teaming arrangements including subcontracting, and certifications that all
individuals assigned to the task order meet the education and experience requirements
for the proposed labor categories as defined in contract. The cost proposal
includes detailed cost/price amounts of all resources required to accomplish
the task. SRA forwards the technical and cost proposal electronically to the
DISA KO and COR and the Task Monitor for concurrent evaluation.
STEP
5 - DISCUSSION/AWARD
The KO requests the TM perform a technical evaluation of the proposals. The
TM may obtain past performance information by requesting such information
from the KO. Discussions or negotiations between the contractor and the TM
will occur only with the prior permission or involvement of the KO. Once the
proposal has been reviewed by the TM, COR, and KO, and all pre-award issues
have been resolved, the KO awards the task order. If awarded the task order,
SRA is authorized to begin work.
|